The summer break is the one time of year a school can be repainted without working around students. It’s roughly seven weeks, and it goes quickly. Most of the jobs that run late in January weren’t held up on site. They were held up in October and November, when decisions weren’t made in time.
If your school is planning painting works over the holidays, these are the things that need to be settled before the end of term.
1. Lock in the scope early
Painting contractors who do school work book out their summer crews early. A scope that’s still being discussed in December often means a smaller crew, a later start, or a contractor you haven’t worked with before.
A good scope lists the buildings and rooms, which surfaces are included (walls, ceilings, doors, frames, external fascias, handrails), and anything that needs repair before painting. If you’re unsure, a walk-through with the contractor will turn a rough list into a priced scope in a few days.
2. Decide on colours and products now
Colour changes are the most common cause of late starts. If the school is changing its colour scheme, get the selections approved by the principal or council before you go to quote.
For classrooms and corridors, ask for a hard-wearing, washable finish. Low-VOC paints are the standard for occupied buildings and mean rooms can be used soon after the final coat.
3. Check for lead paint in older buildings
Buildings painted before the 1970s may have lead-based paint under the newer coats. Disturbing it by sanding releases dust, which is a serious health risk, especially for children.
If your buildings are that age, have the paint tested before the job is priced. Lead removal changes the method, the safety controls and the cost, and you don’t want to find out halfway through the holidays.
4. Plan the order of works
Seven weeks sounds like plenty until you account for other trades. Carpet layers, electricians and furniture removalists often want the same rooms at the same time.
Painting should usually come before new flooring and after any electrical or carpentry work. A simple room-by-room program agreed with all trades before the break avoids rooms being painted twice.
5. Sort out access and site requirements
Things that slow down the first day on site:
- Keys and alarm codes, and who holds them over the break
- Contractor induction and sign-in requirements
- Working with Children Checks, which many schools require of anyone on site
- Where the contractor can park, store materials and wash out
- Whether any holiday programs or vacation care are running on the grounds
If the site will have children on it during the works, the contractor needs to know so they can fence off work areas.
6. Leave a buffer before Term 1
Aim to finish painting at least a week before staff return. That leaves time for touch-ups, cleaning, furniture to go back in, and any defects to be fixed before the first day of term.
The short version
If you want the school repainted over summer, have the scope, colours and any lead testing sorted by mid-November. Then confirm the program and site access before the last week of term.